Sustainable Water Infrastructure Project (SWIP)
Project Information
This project will construct the Sustainable Water Infrastructure Program (SWIP) consisting of three elements.
Element 1: a modular reverse osmosis (RO) unit at the Santa Monica Urban Runoff Recycling Facility (SMURRF), a new shallow brackish and saline groundwater extraction well at the beach, and new solar panels for energy offset.
Element 2: a below grade stormwater and sewer treatment facility at the Civic Center Lot with 1 million gallons per day (MGD) capacity.
Element 3: two new stormwater harvesting tanks at Memorial Park and the Civic Center Lot, with 1.5 million gallon (MG) capacity.
Budget Total
$95,939,393.00
Current Phase
Construction
Phase History
Phase | Start | End |
Design | 2018 Q4 | 2019 Q2 |
Construction | 2020 Q1 | 2021 Q3 |
Other Resources
City Council Action History
Date | Action Type | Outcome |
9/10/2019 | Award of the Design/Build Contract Guaranteed Maximum Price Amendment | Council authorized the construction phase of SWIP by awarding the Guaranteed Maximum Price contract amendment for construction services. |
8/28/2018 | Selection and Award of Sustainable Water Infrastructure Project Design/Build Services Contract | Council awarded a design/build services contract to Kiewit Infrastructure West Co. partnering with Arcadis USA and PERC Water. |
9/12/2017 | Accept State Funding and Award Owner's Engineer Service Contract | Accepted Funding from the State Water Resources Control Board Clean Water State Revolving Fund Program
Award Contract to MWH/Stantec Consulting for Owner's Engineer Services |
9/27/2016 | Adoption of CEQA IS/MND | Adopted CEQA Initial Stud/ Mitigated Negative Declaration |
1/26/2016 | State Funding Application | Applied for California Clean Water State Revolving Fund and Proposition 1 Funding Programs |
|
|