Sustainable Water Infrastructure Project (SWIP)

Project Information

This project will construct the Sustainable Water Infrastructure Program (SWIP) consisting of three elements. Element 1: a modular reverse osmosis (RO) unit at the Santa Monica Urban Runoff Recycling Facility (SMURRF), a new shallow brackish and saline groundwater extraction well at the beach, and new solar panels for energy offset. Element 2: a below grade stormwater and sewer treatment facility at the Civic Center Lot with 1 million gallons per day (MGD) capacity. Element 3: two new stormwater harvesting tanks at Memorial Park and the Civic Center Lot, with 4.5 million gallon (MG) capacity.

Budget Total

$56,880,000.00

Current Phase

Design

Other Resources

City Council Action History

DateAction TypeOutcome
8/28/2018Selection and Award of Sustainable Water Infrastructure Project Design/Build Services ContractCouncil awarded a design/build services contract to Kiewit Infrastructure West Co. partnering with Arcadis USA and PERC Water.
1/26/2016State Funding ApplicationApplied for California Clean Water State Revolving Fund and Proposition 1 Funding Programs
9/12/2017Accept State Funding and Award Owner's Engineer Service ContractAccepted Funding from the State Water Resources Control Board Clean Water State Revolving Fund Program Award Contract to MWH/Stantec Consulting for Owner's Engineer Services
9/27/2016Adoption of CEQA IS/MNDAdopted CEQA Initial Stud/ Mitigated Negative Declaration