City Council Meeting: May 13, 2008

Agenda Item: 8-A

 

To:                   Mayor and City Council

From:              Joan L. Akins, Acting Director - Environmental and Public Works Management

Carol Swindell, Director of Finance

 

Subject:          Five-Year Rate Schedules for Water and Wastewater

 

 

Recommended Action

Staff recommends that the City Council:

1.      approve a five-year plan to increase water rates;

2.      approve a five-year plan to increase wastewater rates;

3.      approve a revision of the rate structure for both water and wastewater to a commodity-only structure to promote water efficiency and conservation;

4.      approve a discounted low income customer water rate for the first tier usage of water;

5.      approve a discounted low income customer wastewater rate for usage corresponding to the first tier water consumption;

6.      approve enhanced funding levels for capital, operating, and rate stabilization reserve funds for both water and wastewater; and

7.      adopt a resolution setting a public hearing on July 8, 2008, in accordance with Proposition 218, to consider water and wastewater rate increases.


Executive Summary

At a study session with Council on April 22, 2008, staff presented updated financial projections and alternate scenarios for water and wastewater rates.  SIx options were presented for water rates and five options were presented for wastewater rates. The discussion focused on staffs recommended option, with and without a one-time cash infusion from the MtBE settlement funds.  Council directed staff to return with what was reflected as   option 5 for water and option 4 for wastewater, which preserved the MtBE settlement funds, changed the rate structure to be all commodity use based, built a reserve over time and continued the pay-as-you-go capital financing model. Following this direction, a the recommended rates are as follows:

 

WATER

FY 08/09

FY 09/10

FY 10/11

FY 11/12

FY 12/13

Presented April 22

11.5

10.5

10.5

10.5

9

Corrected

11.0%

10.5%

10.5%

10.0%

10.0%

 

 

 

WASTEWATER

FY 08/09

FY 09/10

FY 10/11

FY 11/12

FY 12/13

Presented April 22

18

18

15

8

5

Corrected

18.0%

18.0%

15.0%

9.0%

4.0%

 

It should be noted that these rates are slightly different than the percentages shown in the April 22 report. The attached consultant reports on April 22 included the correct tables.

 

Background

In a City Council study session on May 17, 2005, staff presented information addressing the status of the fund balances for the Water and Wastewater funds.  Specifically, expenditures in both of these funds were outpacing revenues.   Options were provided in the study session to balance expenditures and revenues. 

 

A subsequent report to Council on June 21, 2005, provided additional information regarding expenditures and revenues for the Water fund and presented additional options for bringing expenditures and revenues into balance.  Staff indicated in the June 21, 2005 report that consideration of wastewater rate adjustments could be deferred until FY 2006-2007 or FY 2007-2008 depending on actual costs and revenues during the ensuing period.

 

 

 

Council direction to staff received on June 21, 2005 included:

·        Implement a 6% increase to water rates for FY 2005-2006 that would balance revenues and expenditures for one year only;

·        Conduct a water rate study to finalize the additional rate increase amounts required to balance the fund, including examining a restructuring of the tiered system to provide a conservation incentive to reward customers who voluntarily conserve water;

·        Utilize a cost of service approach in any new rate design; and

·        Review practices and procedures to assess efficiencies throughout the operational functions of the Division.

 

Concurrent with the commissioning of a water rate study in 2007, staff also commissioned a wastewater rate study to review the revenue requirements necessary to meet required wastewater operating and capital expenditures as well as existing debt service obligations.

 

 

Existing Wastewater Rates

Established pursuant to a 1996 rate study, the existing wastewater rate structure comprises a fixed service charge plus a commodity charge.   The rate structure has remained unchanged since 1996; however, an annual CPI-based rate increase has been in effect since 2001.

 

The fixed service charge component is assessed to each customer account based on water meter size, and the commodity charges are based on estimated wastewater flows during the bi-monthly billing period.  A discharge factor is applied to the metered water consumption to represent the portion of water usage returned to the wastewater system.  The discharge factors range from 51% for single family residential accounts, to 95% for multi-family residential accounts with more than 4 units.  Typically, single family residential users exhibit the greatest level of outdoor water usage which is not returned to the wastewater system.  All non-residential customers are assigned a discharge factor of 89%.  Commodity charges for non-residential customers vary depending on type of business.

 

In a study session with Council on May 8, 2007, staff presented various options for both water and wastewater rate and structure modifications.  A five year plan was presented for each, with water rate increase recommendations by staff comprising an 11% annual rate increase for water, and a wastewater rate increase plan of 30%, 25%, 20%, 10%, and 0%.  Structural modifications for each were also suggested.  Council was informed that alternative information was pending at the time and that staff would return with updated information, and very likely lower rate increase options at a later date.

 

At a follow-up study session with Council on April 22, 2008, staff presented updated financial projections and alternate scenarios for water and wastewater rates.  Two updated options each were presented for water and wastewater rates (each presented with and without a one time cash infusion alternate).  A change to a commodity-only rate structure was recommended, in addition to a recommendation for enhanced reserve levels in order to provide increased flexibility in the event of unforeseen financial challenges.  Council directed staff to return with the recommendation to approve Option 5 for water and Option 4 for wastewater, as described in detail herein, with the proposed change to a commodity-only rate structure and the enhanced reserve levels.

 

Existing Water Rates

The City provides water service to three customer types: single-family, multi-family and non-residential.  The current water rate structure was adopted in 1996 to provide equity between customer types and among customers within a class. There were no rate changes in 1997 or 1998.  In 1999, a resolution to annually increase rates by the actual Consumer Price Index (CPI) increase was adopted and has been implemented with each annual budget.   A 6% increase was approved by Council for FY 2005/06.

 

The existing water rate is structured so that every single family, multi-family and non-residential customer pays a bi-monthly service charge based on size of the water meter. The rates do not differ by customer class. Customers are also charged a commodity, or usage rate based on the quantity of water used in each two-month billing period. There are three levels, or tiers, of the commodity rate, the purpose of which is to provide financial incentives for water conservation.  As an example, for single family customers, Tier 1 rates are charged on the first 13 hundred cubic feet (HCF: each HCF represents 748 gallons of usage).  Tier 2 rates are charged for usage from 14 to 126 HCF, and Tier 3 rates are charged on any usage above 127 HCF, which very few customers reach.

 

Discussion

Water Rate Study

A water rate study was conducted for the city by The Reed Group, Inc. (Attachment A) Among the objectives of the study were to present a strategy for meeting the utility’s financial obligations for the five year planning period (FY 2007-2008 through FY 2011-2012) and to assess changes to the rate structure in keeping with the city’s sustainability goals to encourage water conservation.  The study confirmed that the cost of operating and maintaining the water system and replacing and upgrading existing facilities exceeds current and projected revenues.

 

The current practice of applying an inflation-only (CPI) rate increase annually will result in all reserve funds being depleted by FY 2008-2009.  Exhibit I summarizes the major categories of cost within the water utility based on the FY 07-08 budget.  The two largest cost categories are Metropolitan Water District (MWD) imported water purchase costs and labor costs.  Both cost categories have exceeded the pace of inflation.  Furthermore, the third largest category of cost (capital improvement projects) should not be correlated to inflation, but to the long-term replacement needs of the water system which greatly exceed the ongoing inflation rate, particularly due to construction cost increases in recent years.  The 15% shown for capital improvement projects in Exhibit I represent current planned annual replacement of the water system and miscellaneous other projects.  A more in-depth examination of long-term water infrastructure upgrade and replacement CIP needs is planned to be conducted during FY 2007-2008.  Water Fund costs also includes funding for programs to increase water efficiency and water re-use by residents, businesses and institutions within Santa Monica.  The analysis confirms that rate increases above the CPI factor are necessary to balance revenues and expenses, and to maintain adequate reserve fund balances over the five year planning period.

Exhibit I

 

Water System Costs, Capital and Operating, by Category

 

 

Financial Strategy Options – Water 

As an enterprise fund, the City’s water utility is expected to be financially self sufficient.   Generally, revenues should match annual expenditures.  Additionally, the city has to date maintained target levels for reserve funds to meet unforeseen operating expense cash flow needs (operating reserve: $1.3 million target level = 10% of O&M), to provide a buffer in the event of a drought or other water supply emergency circumstance which might have adverse affects on revenues (rate stabilization reserve: $1.0 million target level), and to provide a buffer for the variability of capital program expenses (capital reserve: $1.275 million target level).  As further discussed below, target reserve levels have since been revised.

 

With the goal of maintaining financial reserves at acceptable levels throughout the planning period, four rate options were initially developed as alternates to the baseline scenario of continuing with inflation only increases.  These options were presented at the May 8, 2007 Council study session.

 

The following options are summarized in Table 1:

·        Baseline - apply an annual inflation-only (CPI) rate increase; reserve funds are exhausted and fund balance goes negative in FY 2008-2009.

·        Option 1 - apply annual increases in water rates to cover all financial obligations and maintain all reserves at or above target levels each year of the planning period.

·        Option 2 - utilize the $1 .0 million rate stabilization reserve to offset a portion of required rate increases and provide additional time to correct the financial imbalance.  The rate stabilization reserve will be reestablished to the minimum target level by the end of the planning period.  Use of the rate stabilization reserve in this manner is consistent with its intended purpose.

·        Option 3 - utilize the $1.0 million rate stabilization reserve and a portion of the $1.275 million capital reserve to offset required rate increases, providing additional time to correct the financial imbalance.  The rate stabilization reserve and the capital reserve are restored to minimum target levels by the end of the planning period.  Use of the capital reserve may limit flexibility in accomplishing capital program objectives during this period; however, the size of the present capital program contributes to the projected deficit so the use of the capital reserve would be consistent with its intended purpose.

·        Option 4 - equalize annual rate increases; rate increases will be consistent across the planning period.  All reserves will be reestablished to target levels at the end of the planning period.  This option also utilizes the rate stabilization and capital reserves, but to a lesser extent than Option 3 thereby providing additional financial flexibility to respond to unanticipated occurrences during the next five years.

 

TABLE 1 – WATER RATE INCREASE OPTIONS

 

Option 4 had been recommended as the preferred alternative at the May 8, 2007 Study Session.  Subsequently, in light of revised financial information and a review of industry standards regarding reserve level targets, the water rate consultant was requested to revise the previously recommended option to address a revised planning horizon and revised reserve fund levels.   The revised reserve levels include the following:

·        An operating reserve of 25% of the water utility operating budget, exclusive of the capital improvement program and transfers to other funds (increase from 10%)

·        A capital reserve of 50% of annual capital program expenditures (change from a flat $1,275,000)

·        A rate stabilization reserve of $1,000,000 (no change)

 

In addition, in March 2008, MWD, from which the City purchases approximately 85% of its water, approved a 14% increase in treated water delivery rates effective January 1, 2009.  This increase is necessary for MWD in order to purchase additional water supplies in response to a 30% reduction in State Water Project deliveries to Southern California due to court-ordered pumping restrictions in the Sacramento-San Joaquin Delta on top of a long term drought on the Colorado River.

 

Two additional options were developed for water rate enhancements.  In option 5, the revised reserve levels were incorporated, along with the recent information concerning the increase in MWD water rates.   Option 5a is similar to Option 5, with the added consideration of a one time cash infusion of $2.5 million into reserves.  This is a one time cash supplement, and not an ongoing demand.

 

The resulting Options 5 and 5a, presented at the April 22, 2008 Study Session, are detailed in Table 2.

                                 

Table 2 – Water Rate Increase Options 5 and 5a

 

Use of Reserves

July 2008

July 2009

July 2010

July 2011

July 2012

Option 5

Implement updated reserve level targets; Rate stabilization and capital reserves are used, but are fully replenished by the end of the planning period

11.5%

10.5%

10.5%

10.5%

9.0%

Option 5a

Same as option 5 above, but with one-time $2.5 million cash infusion to reserves in the first year.

9.5%

9.5%

9.5%

9.0%

9.0%

 

It should be noted that the percentage increases presented in Tables 1 and 2 address the increases necessary to meet revenue requirements even if the existing rate structure is maintained.  The rate study also takes into account the City’s sustainability goals and ongoing water conservation efforts.  Additionally, all increases indicated in Tables 1 and 2 for FY 2008/2009 are inclusive of the planned CPI increase of 3.7% for FY 08/09.  As detailed in the following section, however, a structural modification to the rates is also proposed.

 

At the April 22, 2008 study session, Council discussed the merits of options 5 and 5a and provided direction to staff to return May 13, 2008 with a final recommendation to adopt option 5.  Subsequently, staff has determined that the numbers presented for option 5 did not match the numbers presented in the consultant’s rate report.  Accordingly, the corrected numbers for option 5 are presented in Table 2a below, and in subsequent Tables 3, 3a, and 4.

 

Table 2a – Water Rate Increase Option 5 (corrected)

 

Use of Reserves

July 2008

July 2009

July 2010

July 2011

July 2012

Option 5 (corrected)

Implement updated reserve level targets; Rate stabilization and capital reserves are used, but are fully replenished by the end of the planning period

11.0%

10.5%

10.5%

10.0%

10.0%

 

Rate Structure Modifications

The proposed rate restructuring eliminates the bi-monthly fixed service charge so that the water bill will be entirely based on actual water usage, thereby improving the water conservation incentive at all levels.  For residential customers, the existing three tier structure is replaced with a four tier structure.  For non-residential customers, a uniform commodity rate is established, applicable to nearly all water use.  A second tier for non residential customers applies at the high end of consumption, in order to provide a strong disincentive for excessive water use.

 

 

The proposed rate structure:

·        Improves the water conservation incentive.  A customer can directly reduce their water bill amount by reducing water consumption.

·        Continues to protect the affordability of basic levels of water use, even as water rates increase.

·        Reflects the cost of providing water service to each group of customers.

·        Maintains rate equity between customer classes and among customers within a class.

 

Recommended Option and Rate Impacts

The options presented in Table 1 (not including the baseline) were prepared in advance of reserve fund level enhancements and before considering the impacts of the MWD rate increase in March 2008.  When the impacts of the enhanced funding levels and the MWD increases are included, the rate impacts are as indicated in Table 2.  As directed by Council, Option 5 (corrected) is recommended for adoption.

 

In Table 3, option 5 (corrected) in combination with the revised commodity-only rate structure, results in a variation of water charge impacts within each customer group proposed for FY 2008/2009.  Rather than a uniform increase to all customers, the actual percentage increase will be less for lower consumption users and more for higher consumption users.  This is true for the first year only, due to the change in rate structure.  In subsequent years, all customer classes will see the same percentage increase in charges.  Table 3a demonstrates this uniform percentage increase for all customer classes in the following year (FY2009/2010).


Table 3

Proposed Water Rates, FY 2008/2009

 

 

Customer

meter size

Bi-monthly water use, HCF

Current Rates & Structure(1)

Option 5(corrected),     w/ Proposed Structure

$

Change(2)

% Change(2)

notes

Single family,

average use

3/4"

35

$75.37

$74.89