Subject: Discussion of Development
Agreement Concept Plans for an Entertainment Production Facility at
Recommended
Action
Staff recommends the City Council discuss the appropriateness and potential public
benefits of the applicant’s Development Agreement proposal for a new
entertainment production facility at
Executive
Summary
This hearing is part of the initial round
of hearings before the Planning Commission and City Council to obtain
preliminary feedback on concept plans for a proposed creative
office/production studio. While a
Development Agreement is exempt from zoning standards, it must comply with the
General Plan. This proposed use is
consistent with the General Plan. It is
also consistent with the City Council direction for this portion of the
industrial area of the LUCE. This
Development Agreement proposal is being processed pursuant to Interim Ordinance
No. 2242 (CCS), which was enacted to prevent the continued piecemeal
development of this area with large blocks of development without adequate
infrastructure, amenities and services.
During the pre-submittal hearing on a Development Agreement proposal for
the
The
Planning Commission prepared recommendations for public benefits associated
with the applicant’s proposal for the three-story, 45 foot high, 153,000 square
foot entertainment production building over a basement and subterranean parking
garage on December 12, 2007. The
Commission also recommends modifying the building design to breakup its long
linear scale. In response to the
Planning Commission’s concern the applicant is preparing a modified concept
design, but that rendering was not available to be transmitted with this report
and will be provided prior to the hearing.
Because
the City is engaged in developing new General Plan policies and vision for this
area of the City, a Development Agreement for this project also needs to
contemplate the LUCE vision so that the project that ultimately returns to the
Planning Commission and City Council not only addresses community concerns, but
its design, uses, features and infrastructure will contribute to the
community.
Staff suggests the Council focus on the following items in considering this matter:
a. The desirability of the proposed use and its
consistency with the neighborhood context;
b. Consistency with the General
Plan;
c. Any alternatives that should
be considered;
d. Any negotiating points that should
be addressed; and
e. Identify desirable
infrastructure/public benefits
If a Development Agreement is initiated, the negotiations between the applicant and the City should:
1) Achieve a design and uses that contemplates the LUCE vision while being consistent with the adopted General Plan;
2) Negotiate public benefits such as open space and pedestrian amenities;
3) Negotiate Transportation Demand Management to reduce single-occupant vehicle trips and vehicle miles traveled; and
4) Negotiate public benefits that improve infrastructure, circulation and use of public transit that is coordinated to encourage similar benefits from the adjacent properties.
Based on feedback that has been received from the Planning Commission and will be received from the City Council, the applicant will determine how or whether to pursue the Development Agreement. If the Development Agreement process is pursued, fiscal impacts to the City would be identified during the negotiation process and addressed in the ultimate proposal to the City Council
Background
The applicant submitted Development Review
(DR 06-009), Design Compatibility Permit (DCP 06-006) and Vesting Tract Map (TM
06-024) applications to develop the site with 54 artist studio condominiums on
August 15, 2006. This project is in the
environmental review stage and has not been scheduled for a public
hearing. Because of the type of
applications and the submittal date, the artist studio condominium project can
be processed without a Development Agreement and would not provide the public
benefits that could be gained from pursuing the entertainment studio
project. While these applications were
being processed with the City, the applicant was contacted by a representative
from a major movie and multi-media entertainment production company to develop
the site for their production headquarters.
As a result, the applicant has placed the artist studio condominium
applications on hold while this Development Agreement proposal is pursued. Those applications will be withdrawn if the
Development Agreement proposal is successful.
Prior
City Council Direction
Following
the public hearing on a Development Agreement proposal for the
|
|
|
|
Zoning Context |
Land Use Context |
The property is
generally surrounded by one and two story commercial buildings occupied by movie
production, industrial, public utility yard and auto repair uses. Properties across
Discussion
Development Agreements are not
quasi-judicial matters like Development Review Permits or Conditional Use
Permits. They are negotiated contracts
between the City and an applicant and are implemented by ordinance. To avoid negotiating a project the City
Council cannot ultimately accept, staff scheduled this preliminary discussion
at the outset of this process. The
Planning Commission reviewed the concept plans at their December 12, 2007
meeting and their recommendations to the City Council are included later in
this report. The City Council’s
discussion will provide direction to staff and inform the property owner of key
issues that need to be addressed during the Development Agreement negotiation
process. Attachment C contains the
applicant’s summary and concept plans.
Applicant’s Project Description
The
applicant proposed two redevelopment alternatives to the Planning Commission;
however the Planning Commission’s discussion was based on the three-story, 45
foot high, 153,000 square foot entertainment production building over a
basement and two-level subterranean parking garage proposal. The basement would contain ancillary
facilities, including media storage vaults, conference and screening
rooms.
The building would be occupied by a single
movie, music, television and video production company. The proposed use is consistent with the
property’s LMSD zoning and Special Office District land use designation. The subterranean parking garage would provide
approximately 412 parking spaces plus four at-grade freight loading spaces that
would be accessed from a two-way driveway from
The applicant has suggested that the
following list of project features will provide public benefit:
1. Open space on the
corner of Stewart and
2. New revenue from the
project to the
3. Opportunities for
high paying jobs for
4. Lighter traffic during peak hours as compared to existing use and general office use;
5. Higher public transit use;
6. The post-production, film and music industry provides high employment with lower impact on the streets, environment and surrounding neighborhoods compared to traditional uses;
7. LEED certified;
8. Pedestrian orientated design;
9. Lionsgate provides social benefits; and
10. As owner, Lionsgate is a good neighbor.
At this early stage in the process, the
proposed conceptual plans are extremely schematic. Comprehensive project plans and alternatives
would be developed during the Development Agreement process based on direction
from the City Council pertaining to the project’s size, scale, uses and public
benefits. As discussed in the General
Plan section below, the project must be consistent with the current General
Plan as well as anticipating the evolving vision of the Land Use and
Circulation Elements (LUCE) update for this area.
General Plan Consistency
The City is actively engaged in developing
new General Plan policies and vision for this area of the City. Although the new policies may not be adopted before
this proposal is ready for final consideration, the evolving LUCE vision is
based on planning principals and community values that should shape any
proposal for this site. Accordingly, the
Development Agreement for this project needs to contemplate the LUCE vision so
that the project that ultimately returns to the Planning Commission and City
Council not only addresses community concerns, but its design, uses, features
and infrastructure will be consistent with community goals.
In this case, the proposed creative arts
studio use is consistent with the adopted Land Use Element and has also been
identified during the recent LUCE public workshops for the industrial area as a
continued appropriate use for the area.
Although additional public hearings will be held to refine the community
vision for this area, creative arts and entertainment use was clearly
identified by the community to be retained in this area.
The subject property is located in the
Special Office District of the General Plan Land Use Element. Land Use Policy 1.8.7 allows a maximum height
of three stories and 45 feet and a maximum floor area ratio (FAR) of 2.0 in
this district. The proposal’s
three-story, 45 feet high, 2.0 FAR is consistent with this policy. The creative office/entertainment production
use is consistent with Land Use Objective 1.8 to “Provide opportunity for
office and advanced technology uses requiring large floor areas.”
The property is approximately ¼ mile
(reasonable walking distance) of the potential Bergamot METRO rail
station. While the LUCE vision is still
being developed, there is community support to identify the areas adjacent to
the Bergamot transit station as future creative arts neighborhoods. Therefore, it appears that this project, as a
creative arts and entertainment use, is consistent with this emerging LUCE
vision and an opportunity to better utilize the future rail transit opportunity
to reduce long term traffic impacts.
Overall Size, Scale and Design
The size of the proposed building is consistent
with the current General Plan. However,
the conceptual plans as presented are extremely schematic and primarily provide
a starting point for discussion. While
the proposal is consistent with recent building trends for this area, staff is
concerned with the building’s 490 foot length, but a number of design options
are available to break-up its apparent mass along
Neighborhood Context
The General Plan provides direction for the
long term development of the City.
Again, the LUCE policies and vision that are currently evolving
represent the key context for evaluating neighborhood compatibility for this
area. Pursuant to the LUCE, the project
needs to:
1)
Create
a walkable environment with appropriate scale;
2)
Provide
public services and amenities such as open space;
3)
Address
needed infrastructure and circulation;
4)
Reflect
use or uses identified in the plan; and
5)
Interface
with the proposed METRO station to the south.
In addition to the General Plan, the type
and scale of existing and future development surrounding the project are used
to evaluate the project’s overall size and scale. Properties on the north side along
Planning
Commission Action
The Planning Commission conducted a public
hearing on this proposal on December 12, 2007.
Based on input from the applicant and the public, the Planning Commission
recommended the following to the City Council:
A copy
of the December 12, 2007 Planning Commission minutes is contained in Attachment
A.
Alternatives
In addition to the recommended action, the City
Council could continue the discussion for analysis of additional options with
agreement from the applicant.
Environmental
Analysis
CEQA
review is not required for the purpose of a preliminary discussion of the
feasibility of a potential project and the appropriateness and potential public
benefits of a Development Agreement for the site (State CEQA Guidelines Section
15262). Environmental analysis will be
completed prior to considering approval if the Development Agreement process is
engaged.
Public Outreach
Sign posting and mailed notices are not
required by Code for this initial discussion procedure; however, notice of the
public hearing was mailed to all owners and residential and commercial tenants
of property located within a (500 foot) radius of the project and published in
the Santa Monica Daily Press at least
ten consecutive calendar days prior to the hearing.
Budget/Financial Impact
Staff costs for the
Development Agreement process are paid from application fees. There is a wide range of public benefits that
the developer could be required to provide pursuant to the Development
Agreement negotiations. The associated
fiscal impact will be determined prior to the Development Agreement returning
for City Council consideration.
Prepared
by:
Bruce Leach, Special Projects
Administrator
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Eileen Fogarty Director, Planning & Community Development |
|
P. City Manager |
ATTACHMENTS:
A.
December
12, 2007 Planning Commission Report
B.
Public
Notification & Comment Material
C.
Proposal
Summary & Plans
ATTACHMENT
A
November
14/ December 12, 2007 Planning Commission Staff Report & Minutes
Planning Commission Report
Planning Commission Meeting: November 14, 2007
(Continued to December 12, 2007)
Agenda Item: 10-A
To: Planning Commission
From:
Subject: Discussion
of Concept Plans to redevelop the property located at
Address:
Applicant:
Recommended
Action
It is recommended that the Planning Commission:
1. Recommend that the City Council initiate the Development
Agreement negotiation and review process;
2. Discuss
the applicant’s Development Agreement proposal and provide direction regarding
its potential public benefits and appropriateness for the redevelopment of the
site.
Executive Summary
The applicant is proposing that the City consider
a Development Agreement to permit redevelopment of the site with a three-story,
115,200 square foot entertainment production building over a subterranean
parking garage. The building would be
occupied by a major movie and multi-media production company. The proposed use is consistent with the
property’s LMSD zoning and Special Office District land use designation.
While a Development Agreement is exempt from
zoning standards, it must comply with the General Plan. Because the City is engaged in developing new
General Plan policies and vision for this area of the City, a Development
Agreement for this project also needs to contemplate the LUCE vision so that
the project that ultimately returns to the Planning Commission and City Council
not only addresses community concerns, but its design, uses, features and
infrastructure will contribute to the community.
Staff suggests the Commission focus on the following items in considering this matter:
a. The desirability of the
proposed use and its consistency with the neighborhood context;
b. Consistency with the General
Plan;
c. Any alternatives that should be considered;
d. Any negotiating points that
should be addressed; and
e. Identify desirable
infrastructure/public benefits
If a Development Agreement is initiated, the negotiations between the applicant and the City should:
5) Achieve a design and uses that contemplates the LUCE vision while being consistent with the adopted General Plan;
6) Negotiate public benefits such as open space and pedestrian aminities;
7) Negotiate Transportation Demand Management to reduce single-occupant vehicle trips; and
8) Negotiate public benefits that improve infrastructure, circulation and use of public transit.
Background
The applicant submitted Development Review
(DR 06-009), Design Compatibility Permit (DCP 06-006) and Tract Map (TM 06-024)
applications to develop the site with 54 artist studios on August 15,
2006. While these applications were
being processed with the City, the applicant was contacted by a representative
from a major movie and multi-media entertainment production company to develop
the site for their production headquarters.
As a result, the applicant has placed the artist studio condominium
applications on hold while this Development Agreement proposal is pursued. Those applications will be withdrawn if the
Development Agreement proposal is successful.
Project / Site Information
The following table provides a
brief summary of the project location.
Project
and Site Information Table
|
Zoning District: |
LMSD (Light
Manufacturing Studio District) |
Site
Location Map |
|
Land Use Element
Designation: |
Special Office
District |
|
|
Parcel Area (SF): |
1.76 Acres (76,795 sq. ft.) |
|
|
Parcel
Dimensions: |
120’ x 640’ |
|
|
Existing On-Site
Improvements (Year Built): |
One-story light
industrial (age of buildings vary from 1948 through 1950s) |
|
|
Rent Control
Status: |
Commercial Exempt |
|
|
Adjacent Zoning
Districts and Land Uses: |
LMSD– South & East LMSD & C5- West R2 – North |
The property is generally
surrounded by one and two story commercial buildings occupied by movie
production, industrial, public utility yard and auto repair uses. Properties across
Discussion
Development Agreements are negotiated
contracts between the city and an applicant that specifies the design details
and requirements of a project. In order
to avoid negotiating a project the City finds unacceptable, this matter was
scheduled to enable a pro-active discussion with the Planning Commission. The Commission’s discussion will help advise
the City Council, provide initial direction to staff and inform the property
owner. The information gathered during
this discussion will be used by the applicant and City Council to evaluate the
potential health, safety and welfare benefits and impacts of the proposal and
potential alternatives. Attachment B
contains the applicant’s summary and concept plans.
Applicant’s Project Description
The applicant proposes that the City
consider a Development Agreement to redevelop the site with a three-story, 115,200
square foot entertain production building over a two-level subterranean parking
garage. The building would be occupied
by a single tenant movie, music, television and video production company. The proposed use is consistent with the
property’s LMSD zoning and Special Office District land use designation. The subterranean parking garage would provide
412 parking spaces plus four at-grade freight loading spaces that would be
accessed from a two-way driveway from
The applicant has suggested that the following list of project features
will provide public benefit:
1. New tax revenue from
the project for the use of
2. New revenue from the
project to the
3. Opportunities for
high paying jobs for
4. There will be no impact on traffic over existing use of the site because work schedules are flexible with the Music, Film, and Post-Production industries. Typical of creative companies, the workday starts staggered after 9:00 A.M. and ends staggered after 7:00 P.M., which is after the morning and evening peak traffic times.
5. There could be more
public transit used because the Post-Production, Film, and Music industries
employ a high percentage of young people, who are more apt to car pool or use
the transit systems. There is a bus line
on
6. The entertainment industry facilities are high paying jobs with lower impact on the streets, environment and surrounding neighborhoods compared to traditional uses.
7. Since this is new
construction, it will present opportunities for a sustainable green designed
building, supporting
8. The new project will replace an older property without pedestrian amenities. A new building with sustainable landscaping and improved design elements is intended to create a pedestrian friendly street scape.
At this early stage in the process, the
proposed conceptual plans are extremely schematic. Comprehensive project plans and alternatives
can be developed during the Development Agreement process based on direction
from the Planning Commission and City Council pertaining to the project’s size,
scale, uses and public benefits. As
discussed in the General Plan section below, the project must be consistent
with the current General Plan as well as anticipating the evolving vision of
the Land Use and Circulation Elements (LUCE) update for this area.
General Plan Consistency
The City is actively engaged in developing
new General Plan policies and vision for this area of the City. Although the new policies may not be adopted
before this proposal is ready for final consideration, the evolving LUCE vision
is based on planning principals and community values that should shape any
proposal for this site. Accordingly, the
Development Agreement for this project needs to contemplate the LUCE vision so
that the project that ultimately returns to the Planning Commission and City
Council not only addresses community concerns, but its design, uses, features
and infrastructure will be consistent with community goals.
In this case, the proposed creative arts
studio use is consistent with the adopted Land Use Element and has also been
identified during the recent LUCE public workshops for the industrial area as a
continued appropriate use for the area.
Additional workshops are scheduled to refine the community vision for
this area; however, creative arts is a use that is expected to be identified as
appropriate for the area in the final proposal.
The subject property is located in the
Special Office District of the General Plan Land Use Element. Land Use Policy 1.8.7 allows a maximum height
of three stories and 45 feet and a maximum floor area ratio (FAR) of 2.0 in
this district. The proposal’s
three-story, 45’ high, 1.5 FAR is consistent with this policy. The entertainment production use is also
consistent with Land Use Objective 1.8 to “Provide opportunity for office and
advanced technology uses requiring large floor areas.”
The property is also located within
reasonable walking distance of the potential Bergamot METRO rail station. While the LUCE vision is still being
developed, there is community support to identify the areas adjacent to the Bergamot transit station
as future creative arts neighborhoods.
Therefore, it appears that this project, as a creative arts and
entertainment use, is consistent with this emerging LUCE vision and an
opportunity to better utilize the future rail transit opportunity.
Overall Size, Scale and Design
The size of the proposed building is within
the size limits of the General Plan.
However, the conceptual plans as presented are extremely schematic and
primarily provide a starting point for discussion. Comprehensive project plans will be developed
during the development agreement process based on direction from the Planning
Commission and City Council pertaining to the project’s size, scale, uses and
public benefits.
Neighborhood Context
The General Plan provides direction for the
long term development of the City.
Again, the LUCE policies and vision that are currently evolving
represent the key context for evaluating neighborhood compatibility for this
area. Pursuant to the LUCE, the project
needs to:
6)
Create
a walk able environment with appropriate scale;
7)
Provide
public services and amenities such as open space;
8)
Address
needed infrastructure and circulation;
9)
Reflect
use or uses identified in the plan; and
10) Interface with the proposed METRO station to
the south.
In addition to the General Plan, the type
and scale of existing and future development surrounding the project are used
to evaluate the project’s overall size and scale. Properties on the north side along
As of the preparation of this report, two letters
from the public in support of the proposal has been received. Public notification of this hearing is
contained in Attachment A.
Alternative
Actions:
In
addition to the recommended action, the Planning Commission could consider the
following with respect to the project:
A1.
Continue discussion for analysis of additional options with
agreement from the applicant
Conclusion
The proposed multi-media production use is
consistent with the current vision for the LMSD area and the likely future
vision for this area. This hearing is
part of the initial round of hearings to determine whether to process a
Development Agreement application.