City Council
Meeting: March 25, 2008
Agenda Item: 1-I
To: Mayor and City Council
From:
Subject: Amendment to Construction Contract for
the
Recommended Action
Staff
recommends that the City Council:
1.
authorize
the City Manager to amend construction contract No. 8652 with Midwest Environmental Control, Inc., for additional abatement
of creosote containing materials in the
amount of $450,000 plus a contingency amount of $45,000, in the event
unforeseen conditions should arise, for a new not to exceed amount of $1,931,513;
and,
1.
authorize the Assistant
Director of Environmental and
Executive Summary
The
site at
Background
Construction of the Annenberg Community Beach Club at
On February 26, 2008, Council approved the second
modification to Contract No. 8652 (CCS) to include additional abatement and
disposal of materials revealed during rehabilitation activities in an amount of
$242,745, including 10% contingency, which resulted in a not to exceed contract
value of $1,436,513, including a 10% contingency and a one-time $7,822 addition
for off-site hazardous abatement services at City Hall. On September 11, 2007, Council approved the first modification
to Contract No. 8652 (CCS) to include additional abatement and disposal of
materials revealed during site demolition in an amount of $438,900, including
10% contingency, which resulted in a not to exceed contract value of $1,193,768,
including a 10% contingency. Council
awarded Contract No. 8652 (CCS) with MEC for selective demolition and the
abatement of asbestos and lead containing materials for an amount not to exceed
$747,046, including a 10% contingency at the Council Meeting held November 14, 2006.
Discussion
Recent rehabilitation activities including excavation for installation
of permanent utilities and site wall footings at the east side of the property and
north side of the historic North House revealed additional unforeseen
sub-surface creosote containing materials necessitating abatement and disposal
of those materials. Project excavation activities are nearing completion. The high prevalence of buried creosote
structural components is common in this area of the beach however, the extent
could not be determined prior to excavation activities.
This modification will require an increase in the contract
in an amount of $450,000, plus a 10% contingency ($45,000), in the event additional
unforeseen conditions should arise, for a total of $495,000. This modification will result in a not to
exceed contract value of $1,931,513, which includes a 10% contingency and a one-time
$7,822 addition for off-site hazardous abatement services at City Hall.
MEC has performed abatement of contaminated materials including
removal and disposal of asbestos, lead, and creosote containing materials and
soil located at the
Financial Impacts & Budget Actions
Funds for the amendment to the construction contract in the
amount of $495,000 are available in account C010520.589000, “415 PCH”.
It is anticipated that staff will need to return to Council
at a later date to replenish all or a portion of these construction funds in
order to complete the project. If
necessary, an alternative source of funds for the additional work will be
identified at that time.
Prepared by: Voneelya Simmons, Project
Manager
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Assistant
Director - Environmental and |
|
P.
Lamont Ewell City
Manager |