March 25, 2008
City Council
Meeting: March 11, 2008
Agenda Item: 8-B
1-H
To: Mayor and City Council
From:
Subject: Concept Design, Modification of Professional
Services Agreement with Kimley-Horn and Associates, Inc. and Appropriation of
Funds for the
Recommended Action
Staff recommends that the City Council:
1. review the concept design options and provide input on the development of a preferred concept design option;
2. authorize the City Manager to negotiate and execute a modification to the professional services agreement with Kimley-Horn and Associates, Inc. in an amount not to exceed $106,000 for design services of the Bicknell Avenue Street Greening Project; and
3. appropriate $106,000 from the Stormwater fund balance for the professional services agreement with Kimley-Horn and Associates.
Executive Summary
The
Kimley-Horn and Associates,
Inc. is recommended for design services associated with the implementation of
this project and has developed the preliminary concepts. The modification to the professional services agreement will not exceed $106,000.
Following appropriation, the agreement will be funded from the
Stormwater fund balance.
Discussion
Federal, state and
local regulations require the City to reduce urban runoff pollution from storm
drain discharges into the
In
developing options for this project, several constraints were identified. The proposed project area has twelve existing
on-street permit parking spaces that need to be preserved. Any reduction to the width of the street must
consider traffic flow and emergency vehicle access. Additionally, operations such as street
sweeping, trash collection, utility access and landscape/tree maintenance must
be maintained.
A
professional services agreement was executed with Kimley-Horn and Associates,
Inc. in August 2007 to conduct one community meeting and develop preliminary
design concepts. Three preliminary
design concepts were developed by Kimley-Horn and Associates, Inc. to implement
the proposed “
Option 1: Install 6 foot wide landscaped infiltration
strips adjacent to both the north and south curbs. This option provides the largest amount of
landscaped infiltration strips, minimizes impervious area and maximizes the
amount of runoff that can be infiltrated.
The existing parking is relocated to the new curb face and the amount of
on-street parking remains the same. The
street is narrowed by approximately 12 feet but sufficient width is maintained
for parking and emergency vehicle access.
The estimated cost for this option is approximately $700,000.
Option 2: Install 3 foot wide landscaped infiltration
strips adjacent to both the north and south curbs and install two 8 foot wide
landscaped median islands in the center of the street. This option provides a sufficient amount of
landscaped infiltration strips and minimizes impervious area. The existing parking is relocated to the new
curb face and the amount of on-street parking remains the same. Additionally, the median islands provide
aesthetic benefits and separation between traffic lanes although medians limit
the amount of continuous right of way available for emergency vehicle access at
the location of the two islands. The
estimated cost for this option is approximately $770,000 to $840,000.
Option 3: Install 4 foot wide landscaped infiltration
strips on the north curb only and provide perpendicular parking along the south
curb. This option slightly reduces the
amount of impervious paving and provides a marginal amount of landscaped
infiltration strips along the north curb only.
This option provides the least amount of infiltration of stormwater
runoff and does not accomplish all the objectives of the demonstration project. Perpendicular parking along the south curb provides
approximately seven additional on-street parking spaces. The street is narrowed slightly due to the
infiltration strip on the north curb and perpendicular parking on the south
curb but sufficient continuous width is maintained for emergency vehicle
access. The estimated cost for this option is $490,000 to $560,000.
The City of
Contractor/Consultant
Selection
On February 8, 2007, a Request for Proposal (RFP) with a preliminary scope of services was posted on the City’s website, soliciting proposals to design the Bicknell Avenue Street Greening Project.
On March 19, 2007, three proposals were received from the following firms: KPFF Consulting Engineers, Kimley-Horn and Associates, Inc. and Psomas. A selection committee consisting of staff from Civil Engineering & Architecture and Environmental Programs Divisions reviewed the proposal. On April 18, 2007, the selection committee interviewed all three consulting firms. The selection criteria included the firm’s technical competence, understanding of the project’s scope, direct experience on similar projects, approach to the work, qualifications of the proposed staff, staffing capabilities to meet the desired time frames, and cost of services. Based on the proposals and interviews, the selection committee recommended Kimley-Horn and Associates, Inc. to provide design services for this project.
After considering the design services cost proposal, it was decided to enter into an initial contract with Kimley-Horn and Associates, Inc. to develop conceptual design options and facilitate initial community outreach. On August 9, 2007, a professional services agreement was executed for $34,000 with Kimley-Horn and Associates, Inc. to develop a concept design for the Bicknell Green Street Project. It is now proposed that a modification to the professional services agreement is executed with this firm to finalize the concept design and develop schematic plans for the recommended option. Upon approval of the final concept design another modification to the professional services agreement will be necessary to develop final plans and specifications to construct the proposed improvements.
Community Outreach
On
November 29, 2007, a community meeting was held to discuss the objectives of
the project and solicit input from the community. A mailer was sent to approximately 350
residents adjacent to the project area to notify the community of the upcoming
public meeting. Nine members of the
public participated in the meeting. Five
of the nine members of the public were
At
the community meeting, residents indicated that although street parking is
limited on this block, there is no desire to add additional parking, as there
is sufficient parking available on
Financial Impacts
& Budget Actions
Construction of the project will be primarily funded by the State Water Resources Control Board through a Proposition 50 grant for $450,000. The total project cost, including design services and construction, is estimated to be approximately $700,000. During the design process, staff will confirm funding options for the amount in excess of the available grant funds. At this time, the source of additional funds is likely to be Measure V (as adopted by Council on September 25, 2007). Potential increased maintenance costs associated with these improvements will also be evaluated during final design.
The following budget action is needed to make funds
available for the contract: appropriate $106,000 from 34 fund balance to
account number C340588.589000 (Stormwater System Improvement). Future appropriations will be required to
modify the professional services agreement to complete final construction
documents upon approval of the final concept design and to execute a
construction contract to implement the improvements.
Prepared by:
|
Approved: |
|
Forwarded to Council: |
|
|
|
|
|
Craig
Perkins Director -
Environmental and |
|
P. City Manager |
|
|
|
|
Attachments: 1.
Option 1 – Bicknell Avenue Plan
2. Option 1 – Bicknell
Avenue Cross-section
3. Option 2 – Bicknell
Avenue Plan
4. Option 2 – Bicknell
Avenue Cross-section
5. Option 3 – Bicknell
Avenue Plan